Retail Park, Skegness

This phase started when Skegness Town AFC relocated to Wainfleet Road, The works included the reduced level dig of the existing football pitch and to demolition the old club house / outbuildings. With the introduction of an Aldi Food store unit (19,000 sq ft), an M&S unit (15,000sq ft), a B&M unit (25,000 sq ft) and a Pets at Home unit (5,000 sq ft). The units are steel framed buildings sitting on Controlled Modulus Columns (CMC) and are cladded with composite panels, brickwork and shopfront glazing. In addition to this the Aldi unit has a large section of James & Taylor Terracotta rain screen cladding. External works included 278 works the provision of 227 car parking spaces in tarmacadam and permeable paving, car park lighting and street furniture.
Two methods that where adopted on this scheme that are worth a mention include The Controlled Modulus Columns (CMC) and the permeable paving. Controlled Modulus Columns (CMC) is used to improve the soil characteristics of a compressible soil layer on a building perimeter scale, which reduces compressibility by use of semi-rigid soil reinforcement columns. Unlike other piling solutions that are designed to support the entire load of the structure, CMC increases the stiffness of the soil mass to the building footprint reducing both total and differential settlements by sharing the load of the structure between the soils and the CMCs. Part of the load of a structure is transferred to the underlying layers through the Controlled Modulus Columns. The improved soil mass thus behaves as a composite soil/cement ground improvement system with enhanced stiffness characteristics. The second method was the permeable paving, this system offers SuDS source control benefits: attenuation prior to gradual release to the main drain, water quality benefits due to filtration and the potential for significant above ground attenuation on site due to the planar nature of the surface and incorporation of surrounding kerbing. The preliminary calculations indicate that a surface water storage volume of 535m3 is required within the permeable paved car park area to provide the appropriate level of attenuation. The preliminary event is 40.7 litres per second which offers a reduction on the existing mean annual peak discharge rate.
This phase was delivered on time and within budget.

TIME LAPSE  OF THE PROJECT  click here

 

More Retail Projects »

Retail Park, Skegness , Jessops Construction Ltd
Retail Park, Skegness , Jessops Construction Ltd
Retail Park, Skegness , Jessops Construction Ltd
Retail Park, Skegness , Jessops Construction Ltd
Retail Park, Skegness , Jessops Construction Ltd
Retail Park, Skegness , Jessops Construction Ltd
Back to top

Category:
RETAIL

 

Area:
Lincolnshire

 

Location:
Burgh Road, Skegness

 

Client:
Quora (Skegness) Ltd

 

Architect:
West Hart Partnership Ltd

 

Structural engineer:
Breakwell Sumner Partnership Ltd

 

Form of contract:
JCT Design and Build Contract 2011

 

Value:
£6.05m

 

Project period:
41 weeks